UPDATED: 01/11/2018 — see Change Log
OWNER: Simplot Phosphates (J.R. Simplot)
PROJECT: Brownfield ammonia plant
SUMMARY STATUS: Operational
Simplot began building its new ammonia plant, adjacent to its existing phosphate fertilizer plant, in October 2014. The project was initially scheduled to be complete in Q3 2016, but delays pushed this back. The new plant was mechanically complete in March 2017 and became fully operational in September 2017. Simplot's investment is "one of the largest in company history," and makes it self-sufficient for ammonia.